Which personnel are minimum members of a crane team?

Prepare for the NAVFAC P-307 Training Exam. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your test!

The minimum members of a crane team include the crane operator and the rigger-in-charge. This pairing is essential because the crane operator is responsible for the operation and control of the crane, while the rigger-in-charge ensures that materials are safely secured and properly rigged for lifting. Their collaboration is crucial for safe and effective crane operations.

The crane operator must be fully aware of the rigging process and the load’s characteristics, which is where the rigger-in-charge plays a vital role. This rigger is responsible for directing the rigging crew and ensuring that all safety protocols are followed. Together, these two positions form a fundamental unit that enables safe lifting operations.

Other roles, while important, are not considered minimum requirements for the crane team. Supervisors and additional crew members may assist and provide support but are not necessary for the basic operation and safety of each lift.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy